Power Generation Technology ›› 2025, Vol. 46 ›› Issue (3): 600-606.DOI: 10.12096/j.2096-4528.pgt.23174

• New Power System • Previous Articles    

Study on Dredging Strategy and Electricity Price Calculation of Pumped Storage Power Station in Xinjiang

Changling LI1,2, Xiqiang CHANG3, Hao LU1, Zhizheng HU1   

  1. 1.School of Electrical Engineering, Xinjiang University, Urumqi 830000, Xinjiang Uygur Autonomous Region, China
    2.Research Institute of Economics and Technology, State Grid Xinjiang Electric Power Co. , Ltd. , Urumqi 830000, Xinjiang Uygur Autonomous Region, China
    3.Power Dispatch Control Center, State Grid Xinjiang Electric Power Co. , Ltd. , Urumqi 830000, Xinjiang Uygur Autonomous Region, China
  • Received:2024-04-05 Revised:2024-07-02 Published:2025-06-30 Online:2025-06-16
  • Contact: Hao LU
  • Supported by:
    Xinjiang Natural Science Fund for Distinguished Young Scholars(2021D01E08);Natural Science Foundation of Xinjiang Uygur Autonomous Region(2021D01C044);Second Key R&D Special Project of the Autonomous Region in 2022(2022B01019)

Abstract:

Objectives Under the current electricity price mechanism, it is difficult for Xinjiang pumped storage power station to fully recover the cost through the arbitrage of peak-valley price difference and participation in electric auxiliary services. Therefore, the capacity and electricity charge dredging mechanism of pumped storage power station is studied. Methods Based on the calculation of the electricity cost of Xinjiang pumped storage capacity, the problems existing in the cost dredging are analyzed. The dredging path of “market-oriented + transmission and distribution electricity price” is proposed for Xinjiang pumped storage power station. That is, the cost is recovered by transmission and distribution price before the maturity of power market construction, and the cost is recovered by marketization after the maturity of power market construction. Results Compared with the pure transmission and distribution electricity price recovery, the “market-oriented + transmission and distribution electricity price” method has higher feasibility in dredging capacity electricity price and the increase of transmission and distribution electricity price decrease by more than 90%, which is a feasible model to calm the excessive rise of transmission and distribution electricity price. Conclusions As a supplementary scheme for the operation cost recovery of pumped storage power stations, the research results will provide a broad market trading space for the pumped storage power stations.

Key words: pumping and storage power station, cost recovery, cost management, power market, electricity price measurement