Power Generation Technology ›› 2017, Vol. 38 ›› Issue (5): 45-50.DOI: 10.3969/J.ISSN.2095-3429.2017.05.011

Previous Articles     Next Articles

Analysis of Different Reconstruction Technology for Heating Supply with High Back Pressure of 135MW Grade Steam Turbine

LIU Guangyao1, WANG Xuedong1, SONG Ang2, LIU Chuanling2   

  1. 1. Huadian Electric Power Research Institute, Hangzhou 310030, China;
    2. Shandong Branch of Huadian Electric Power Research Institute, Jinan 250014, China
  • Received:2017-08-07 Published:2017-10-30 Online:2017-10-30

Abstract: There are nine 135MW grade pure condens-ing units and extraction-condensing units with high back pressure heating in the Shandong regional power grid.There are four types of retrofit schemes.In this paper, the characteristics and modification of four kinds of retrofit schemes listed.Through thermal performance test, the eco-nomic indexes after reformed are obtained and analyzed.For the unit reconstructed its LP cylinder current,its modi-fied LP cylinder efficiency is the highest.Because of influ-ence of heat load,circulating water flow and retrofit schemes,four units can not operate without extraction flow during heating period, resulting in lower power capability and higher heat consumption rate.

Key words: 135MW grade, condensing steam tur? bine, circulating water heating, high backpressure retrofit, flow passage reform of LP cylinder